Industrial CFD
A guide to calculating the ROI of CFD simulation in industrial processes
The whitepaper compares five physical prototyping cycles with a CFD campaign followed by two cycles, using a cost model with four separate classes. Every figure in the example is an illustrative assumption, not a market price or Cubit data.


The whitepaper to keep
6 pages with formulas, scenarios and sensitivity analysis (PDF in Italian).
In this article
A technical director choosing between another round of physical prototyping and a computational fluid dynamics (CFD) campaign receives estimates that cannot be compared directly: the prototype hits the cash account, the campaign hits engineering hours and licences, and the two routes affect the schedule in different ways. This guide calculates the ROI of CFD simulation by comparing, for the same component, five physical prototyping cycles with a CFD campaign followed by two physical cycles, the first to correlate the model and the second as the final test.
With their own figures, readers can build a cost model with four separate classes (cash, valued internal hours, calendar time, opportunity cost), with formulas whose denominators are stated for net saving, ROI and break-even, and check it on a recalculable example that also covers the cases where CFD does not pay. All values are illustrative and can be changed.
Physical prototyping versus CFD with a final test
The decision concerns a single component with a fluid dynamic function and a project that plans, from the outset, five build-and-test cycles. Scenario A runs all of them. In scenario B a CFD campaign replaces three cycles: two physical tests remain, one on the initial prototype, which provides the measurement used to correlate the model, and a final one on the chosen configuration. Scenario B is called hybrid because it combines computation and testing. Neither scenario eliminates prototypes, and the final test appears in both.
The comparison is differential, meaning that only what changes from one scenario to the other counts. Requirements definition, concept design, industrialisation, homologation tests and every cost the project bears anyway stay out because they are common to both. What goes in: building the prototypes, the tests, the hours of those who prepare and interpret them, the numerical campaign with its licences and computing, and the hours spent reviewing and validating the model.
The hybrid scheme is the one Cubit practises. The CFD consulting page lists the numerical campaign and numerical-experimental correlation among its activities, and Cubit’s article on CFD and the towing tank regards tests as irreplaceable when high accuracy is needed or when numerical methods are not yet reliable enough.
The supercavitating foil designed for Syroco, which is chasing the sailing speed record, shows the sequence: more than 200 profiles and 20 foils evaluated numerically, 25% less drag than the reference configuration thanks to multidisciplinary optimisation, then a campaign in the cavitation tunnel of the IRENAV institute in Brest to validate the calculations. That result belongs to that project and does not transfer to other components.

Cost items and formulas
Cost classes
Every item in the comparison belongs to one of four classes, and the classes are not added together without a rule. Cash is the outlay to third parties: prototypes, tests at external facilities, the licence share charged to the project, computing, logistics. Valued internal hours are those of staff already on the payroll, multiplied by a fully loaded hourly rate: they measure internal capacity committed, not money spent.
When the CFD campaign frees up hours, reassigning staff to other work can create value, but on its own it reduces neither salaries nor other outlays: valued capacity and cash saving are therefore two distinct results. A real cash saving exists only if a verifiable outlay falls, for instance a prototype order not placed, a facility test not booked, overtime or an external collaboration not triggered. Calendar time is measured in weeks. Opportunity cost is the value of delaying or bringing forward the launch, and it applies only if the launch date generates margin and the physical cycle sits on the critical path.
| Item | Scenario A (5 cycles) | Scenario B (CFD + 2 cycles) | Class |
|---|---|---|---|
| Engineering hours of the physical cycle | 5 cycles | 2 cycles | internal hours |
| CAD preparation of the prototype | 5 cycles | 2 cycles | internal hours |
| Coordination | 5 cycles | 2 cycles | internal hours |
| Prototype, facility test, logistics | 5 cycles | 2 cycles | cash |
| Test technicians’ hours, review of results | 5 cycles | 2 cycles | internal hours |
| CFD engineering, CAD and mesh preparation, solver and models | none | CFD campaign | internal hours |
| Model review and validation | none | CFD campaign | internal hours |
| Solver licence (incremental share), computing/HPC | none | CFD campaign | cash |
| Time to final configuration | 5 cycles | campaign + 2 cycles | calendar time |
Table 1. Cost items by scenario and class.
Formulas and double counting
In the formulas M is cash in euros, H the hours, r the fully loaded hourly rate in euros per hour, N the cycles of scenario A and n_ev the cycles avoided. If the final test of scenario B costs more than an ordinary cycle, the difference is ΔC_test, in euros.
Cost of one physical cycle C_c = M_c + r × H_c [€]
Cost of the CFD campaign C_CFD = M_CFD + r × H_CFD [€]
Investment I = C_CFD + ΔC_test [€]
Net saving S = n_ev × C_c − I [€]
Return, ratio R = S / I [dimensionless]
Return, percentage ROI = 100 × S / I [%]
Break-even, cycles avoided n* = I / C_c [cycles]
Break-even, cycle cost C_c* = I / n_ev [€]
The ratio R is dimensionless and the ROI is its percentage form: with S = €76,250 and I = €68,500, R = 1.113 and ROI = 111.3%. Three rules avoid double counting. Every hour enters once only, in the internal hours class, at rate r. The time difference ΔT = N × t_c − (t_CFD + (N − n_ev) × t_c), in weeks, is valued only as the opportunity cost O = ΔT × m_s, where m_s is the incremental margin lost for each week of delay; O stays outside S and the base ROI.
The margin m_s is not automatically the same thing as the team’s hours, because it measures the effect of the launch date on revenue and not the staff commitment: before using it, check that it does not include benefits or costs already present in S or I, such as hours, overtime, penalties or supplies. An ROI that includes time, 100 × (S + O) / I, is reported on a separate line and states that it includes O. Finally, hours saved turn into cash only if verifiable outlays fall, which is why the example keeps cash and hours apart.
A worked example of CFD simulation ROI

Assumptions
The case is a fluid dynamic component of medium complexity, for instance a duct with a heat exchanger. It does not come from a Cubit project or from a customer’s costs: the numbers are chosen to be recalculable and replaceable.
| Parameter | Value |
|---|---|
| Fully loaded hourly rate r | €75/h |
| Physical cycles in scenario A, N | 5 |
| Cycles avoided in scenario B, n_ev | 3 |
| Duration of one physical cycle t_c | 7 weeks |
| Duration of the CFD campaign t_CFD | 10 weeks |
| Simulations in the campaign and core-hours per simulation | 40 and 2,000 |
| Computing cost | €0.05 per core-hour |
| Margin lost per week of delay m_s | €6,000/week |
| Solver licence, share charged to the project | €12,000 |
| Extra cost of the final test ΔC_test | €0 |
Table 2. Example parameters. Every value can be changed; the hours per item are in tables 3 and 4.
Scenario A, five physical cycles
Scenario A repeats the same cycle five times. Hours are per cycle and the euro columns are already multiplied by r.
| Item | Class | Per cycle | Five cycles |
|---|---|---|---|
| Engineering: design change, test plan, data analysis | internal hours | 150 h = €11,250 | 750 h = €56,250 |
| CAD preparation of the prototype | internal hours | 30 h = €2,250 | 150 h = €11,250 |
| Test technicians | internal hours | 60 h = €4,500 | 300 h = €22,500 |
| Review of results | internal hours | 20 h = €1,500 | 100 h = €7,500 |
| Coordination | internal hours | 10 h = €750 | 50 h = €3,750 |
| Supplier prototype | cash | €18,000 | €90,000 |
| Test at external facility | cash | €9,000 | €45,000 |
| Logistics | cash | €1,000 | €5,000 |
| Scenario A total | €48,250 | €241,250 |
Table 3. Scenario A. Cash €140,000, valued internal hours €101,250 (1,350 h).
Scenario B, CFD campaign and two physical cycles
Scenario B adds the CFD campaign to two physical cycles identical to those in table 3.
| Item | Class | Hours | Euros |
|---|---|---|---|
| CFD engineering: set-up, post-processing, report | internal hours | 320 h | €24,000 |
| CAD and mesh preparation | internal hours | 160 h | €12,000 |
| Solver and models: choice of physics, convergence | internal hours | 80 h | €6,000 |
| Review and validation: mesh independence, correlation, review | internal hours | 100 h | €7,500 |
| Coordination | internal hours | 40 h | €3,000 |
| Solver licence, incremental share charged to the project | cash | €12,000 | |
| Computing/HPC: 80,000 core-hours × €0.05 | cash | €4,000 | |
| CFD campaign total, C_CFD | 700 h | €68,500 | |
| Remaining physical tests: 2 cycles × €48,250 | cash and hours | 540 h | €96,500 |
| Scenario B total | 1,240 h | €165,000 |
Table 4. Scenario B. Cash €72,000 (€16,000 for the campaign and €56,000 for tests), valued internal hours €93,000.
| Quantity | Scenario A | Scenario B | Difference |
|---|---|---|---|
| Cash | €140,000 | €72,000 | −€68,000 |
| Valued internal hours | €101,250 (1,350 h) | €93,000 (1,240 h) | −€8,250 (−110 h) |
| Total cost | €241,250 | €165,000 | −€76,250 |
| Calendar time | 35 weeks | 24 weeks | −11 weeks |
| Opportunity cost O, outside S and the ROI | 11 × 6,000 = €66,000 |
Table 5. Result of the example.
Result
With the assumptions of table 2, the net saving is S = 3 × 48,250 − 68,500 − 0 = €76,250, the ROI is 76,250 / 68,500 = 111.3% and break-even is at n* = 68,500 / 48,250 = 1.42 cycles avoided, in practice two whole cycles.
The ROI is calculated on full cost, cash and hours together, and the net saving splits into two parts of different nature. The €68,000 of cash is the difference between €84,000 of outlays avoided (3 cycles × €28,000) and the €16,000 of cash spent on the campaign: it becomes a real cash saving only if the supplier orders and facility tests not carried out show up as orders and invoices not issued. The remaining €8,250 is valued internal capacity (110 h less): if staff are reassigned it frees time and can create value, but on its own it does not reduce outlays. The 700 engineering hours of the campaign remain a real commitment.
The two thresholds below each hold with the other parameter fixed. With three cycles avoided and the assumed CFD effort, the break-even cycle cost is €22,833, or 47.3% of the assumed value. With three cycles avoided and the assumed cycle cost, break-even holds up to 1,716 hours of CFD effort (1,716.7 rounded down), that is 2.45 times the 700 assumed, with the campaign’s cash unchanged at €16,000.
The durations in the example are added in series, without overlapping the campaign and the correlation test: an overlap would increase the calendar gain. Amounts are rounded to the euro, percentages to one decimal place and break-even to two. The €66,000 opportunity cost applies only if the launch depends on that path, and it stays outside the base ROI because it is an estimate of incremental margin, not a cost borne by the project.
Sensitivity and break-even
Whether CFD pays depends on three uncertain quantities: the effort of the campaign, the number of cycles the simulation really replaces and the cost of what is avoided. Table 6 varies the first two, with the cycle cost and campaign cash of the example.
| CFD effort (campaign cost) | 1 cycle avoided | 2 cycles avoided | 3 cycles avoided | 4 cycles avoided | Break-even n* |
|---|---|---|---|---|---|
| 700 h (€68,500) | −€20,250 / −29.6% | €28,000 / 40.9% | €76,250 / 111.3% | €124,500 / 181.8% | 1.42 |
| 1,050 h (€94,750) | −€46,500 / −49.1% | €1,750 / 1.8% | €50,000 / 52.8% | €98,250 / 103.7% | 1.96 |
| 1,400 h (€121,000) | −€72,750 / −60.1% | −€24,500 / −20.2% | €23,750 / 19.6% | €72,000 / 59.5% | 2.51 |
Table 6. Net saving S and ROI, by CFD effort and cycles avoided.
The column with 4 cycles avoided describes a scenario different from the base case: it leaves a single physical test, whereas the base case keeps two. It assumes that correlation data are already available and reusable, for instance from a previous project on the same type of component. Correlation is still required; it simply does not need a new physical cycle. If the data are missing, the correlation cycle comes back and the case returns to the column with 3 cycles avoided.
The base case (700 h, 3 cycles) gives 111.3%. If the effort grows by 50% and the cycles avoided drop to two, the saving is €1,750: break-even, in practice. If the simulation avoids a single cycle, the campaign costs more than it saves at every effort level considered, down to −€72,750. Within the ranges of table 6, one cycle avoided fewer weighs more than a 50% increase in hours: the first takes €48,250 off the saving, the second €26,250.
Cost of the avoided cycles
Table 7 instead varies the cost of what is avoided, with three cycles avoided and the base campaign.
| Physical cycle cost relative to the assumption | Cycle cost | Net saving S | ROI |
|---|---|---|---|
| 50% | €24,125 | €3,875 | 5.7% |
| 80% | €38,600 | €47,300 | 69.1% |
| 100% | €48,250 | €76,250 | 111.3% |
| 120% | €57,900 | €105,200 | 153.6% |
Table 7. Net saving and ROI as the cost of the avoided cycles varies.
Low-cost prototypes push break-even towards a larger number of cycles avoided, because C_c falls in the denominator of n*. A more expensive final test, with ΔC_test of €10,000, brings I to €78,500 and the saving to €66,250, with an ROI of 84.4%. The same caution applies to time: 11 weeks count as O only with a documented margin per week, and they are not part of the result in table 6.
Data to collect
To replace the assumptions with your own values, the data come from project administration, test reports and computing logs.
- The history of the latest similar projects: number of cycles, hours per item (engineering, CAD, test technicians, review, coordination), outlays for prototype, test and logistics, weeks between the prototype request and the test report.
- The fully loaded hourly rate and how it is calculated, in particular whether it includes overheads.
- The list of mandatory tests, such as homologation or contractual requirements, that the simulation under consideration does not replace and that therefore belong to the common costs.
- For each cycle, the design change it brings and whether it falls within the range of the validated model: n_ev depends on this.
- Licences and computing capacity already available, with the incremental (not list) cost and the execution queue.
- The experimental data usable for correlation: measured quantity, boundary conditions, measurement uncertainty.
- The margin per week of delay and confirmation that the physical cycle sits on the critical path to launch.
What makes the estimate of avoided cycles credible
The number of cycles avoided depends on the validation of the model. In the 2008 version of the NASA-STD-7009 standard, verification is the process of determining that the computational model correctly represents the mathematical model and its solution, while validation is the degree to which the model represents the real world for its intended use. The ASME V&V 20-2009 standard (reaffirmed in 2021) quantifies simulation accuracy for a specific variable at a validation point, with the experimental conditions reproduced, and leaves out accuracy at the other points, which depends on engineering judgement about the family of problems.
For the economic model this leads to a choice made in this guide, not a requirement of the two standards: a cycle counts as avoided only for variants that stay within the validated range, while a variant outside that range brings back a physical cycle and moves the project one column to the left in table 6. The criteria that follow are also those adopted in this guide. The assessment states the acceptance criterion for the comparison with measurement before the simulations are run, estimates the numerical uncertainty from mesh independence and the measurement uncertainty, assigns n_ev variant by variant and entrusts the review of the correlation to someone who did not build the model. Cubit’s towing tank article recalls a similar distinction in the International Towing Tank Conference guideline: numerical uncertainty is derived from the simulations themselves, while modelling error is measured by comparing the model with experimental data.
Technical assessment with Cubit
Cubit provides fluid dynamic design consulting with numerical campaigns and numerical-experimental correlation, and the software listed on the service page includes Star-CCM+, Ansys Fluent and OpenFOAM. The method in this guide is a proposal that readers can apply to their own case: recalculate the tables with real hours and costs, identify the experimental case on which to validate, assign the cycles avoided per variant and estimate the CFD effort. It does not describe a contractual offer or a service with predefined content, and the outcome may well be that for that component simulation does not pay.
Anyone wishing to compare their own case with this model can contact Cubit for consulting or a technical assessment, writing from the Contact page and stating the component, the planned test cycles and the data already available.
Sources consulted
- NASA-STD-7009, Standard for Models and Simulations, approved 11 July 2008, glossary of verification and validation.
- ASME V&V 20-2009 (R2021), Standard for Verification and Validation in Computational Fluid Dynamics and Heat Transfer.
- Cubit, CFD Consulting.
- Cubit, CFD simulation and the towing tank in hull design (in Italian).
- Cubit, Contact us.
The economic model and all numerical values are Cubit’s illustrative elaborations and do not come from these sources.
Text prepared with the help of artificial intelligence and reviewed by Cubit.
What to take into the project
In the whitepaper example, the CFD campaign with two physical cycles costs €76,250 less than five cycles, with an ROI of 111.3% calculated without counting time.
Have a design problem to dig into? Compare requirements and available data with the Cubit team.
Talk to Cubit